Traffic Alerts
{"effect":"fade","fontstyle":"normal","autoplay":"true","timer":4000}

Work Continues on Phase II of I-59/20 Bridge Project (Update)

Posted on: January 3, 2017 at 8:03 pm

FOR IMMEDIATE RELEASE

December 29, 2016

 

MEDIA ADVISORY

 

Work Continues on Phase II of I-59/20 Bridge Project (Update)

Central Business District (CBD) Interchange and Bridge Replacement Project

 

BIRMINGHAM – Weather permitting, the Alabama Department of Transportation will continue a project for new bridge foundation work to improve the I-59/20 and I-65 Interchange as follows:

 

  • A double right lane closure will take place on I-65 northbound between the I-59/20 Interchange and 16th Street North exit ramp for bridge demolition activities (12th Court North Bridge).

–          Tuesday, January 3 at 8 p.m. and ending Wednesday, January 4 8 a.m.

 

  • A rolling road block at 15 minute intervals will take place at the on-ramp from I-59/20 southbound to I-65 northbound for bridge demolition activities (12th Court North Bridge).

–          Tuesday, January 3 at 11 p.m. and ending Wednesday, January 4 at 5 a.m.

 

  • A single right lane closure will take place on I-65 southbound between the 16th Street North exit ramp and the I-59/20 Interchange for bridge demolition activities (12th Court North Bridge).

–          Wednesday, January 4 at 7 p.m. and ending Thursday, January 5 at 5 a.m.

 

  • A rolling road block at 15 minute intervals will take place at the off-ramp from I-65 southbound to 6th Avenue North for beam erection activities.

–          Thursday, January 5 at 11 p.m. and ending Friday, January 6 at 5 a.m.

 

  • A single left lane closure will take place on I-65 southbound between the16th Street North exit ramp and the I-59/20 Interchange for bridge demolition activities (12th Court North Bridge).

–          Friday, January 6 at 7 p.m. and ending Saturday, January 7 at 5 a.m.

 

All temporary traffic control signage and warnings will be in place.

 

This work is a part of Phase II of the I-59/20 Central Business District (CBD) Interchange and Bridge Replacement Project.

 

Motorists are requested to consider using alternate routes, adjust arrival/departure times, observe work zone speed limits and other work zone signs, and use extreme caution in this area. ALDOT thanks motorists for their patience during this Construction Operation to improve Alabama’s roadways.

 

ALDOT’s mission is to provide a safe, efficient, environmentally sound transportation network across Alabama. For additional information please visit our project website www.5920bridge.com and for traffic alerts and updates follow us on Facebook and Twitter @5920bridge.

 

 

# # #