The “Long Route” involved re-routing I-59/20 near Tallapoosa Street west across I-65 and US-78, before rejoining with the existing I-59/20 corridor west of Arkadelphia Road. It shared the same disadvantages and costs associated with traversing the Village Creek floodplain as the short plan.

However, due to the width required for this interstate “corridor,” and that it must have avoided the Burlington Northern Railroad Yard, ALDOT’s study shows the long route would have require the demolition of nearly all the businesses along the existing Finley Boulevard Corridor.

If planning were to start today, the long re-route would take at least 28 years to complete, and cost over $2 billion.

ALDOT did not believe either the short or long re-route alternative was achievable.