I-59/20 Bridge Project Update

April 23, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting:

  • 15th Street N between Rev. Abraham Woods and 12th Avenue N will be closed, Friday, April 24th through Thursday, April 30th from 8 a.m. until 5 p.m. for curb/gutter installation.
  • 19th Street North from Rev. Abraham Woods to 10th Street will be closed, Thursday, April 16th through Thursday, April 23rd from 12 a.m. until 11: 59 p.m. for culvert installation.
  • 16th Street between Rev. Abraham Woods and 10th Avenue N will be closed Thursday, April 23rd through Thursday, April 30th from 12 a.m. until 11:59 p.m. to install drainage.
  • 25th Street N between Rev. Abraham Woods and Richard Arrington Blvd. will be a single right lane closure Thursday, April 23rd through Thursday, April 30th from 12 a.m. until 11:59 p.m. for curb/gutter removal/install.
  • 25th Street S between Rev. Abraham Woods and Richard Arrington Blvd. will be a single right lane closure Thursday, April 23rd through Thursday, April 30th from 12 a.m. until 11:59 p.m. for curb/gutter removal/install.
  • Richard Arrington Jr. Blvd. between Caraway and 28th Street will be closed Thursday, April 23rd through Thursday, April 30th from 12 a.m. until 11:59 p.m. for roadway work and painting.
  • Richard Arrington Jr. Blvd. between 25th Street and Carraway Blvd. will be closed Thursday, April 23rd through Thursday, April 30th from 12 a.m. until 11:59 p.m. for grading and cleanup.

Detour signs will be in place where necessary. Please keep in mind that all construction plans can change due to weather and other factors. As always, use caution and obey the posted speed limits.

This work is a part of the I-59/20 Central Business District (CBD) Interchange and Bridge Replacement Project.

Motorists are requested to consider using alternate routes, adjust arrival/departure times, observe work zone speed limits and other work zone signs, and use extreme caution in this area. ALDOT thanks motorists for their patience during this Construction Operation to improve Alabama’s roadways.

ALDOT’s mission is to provide a safe, efficient, environmentally sound transportation network across Alabama. For traffic alerts and updates, please visit www.5920bridge.com, utilize the ALGO traffic app, and follow us on Facebook, Instagram, and Twitter.