I-59/20 Bridge Project Update

March 26, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting:

  • 19th Street North from Rev. Abraham Woods to 10th Street will be closed Thursday, March 26th through Thursday, April 2nd from 12 a.m. until 11: 59 p.m. for culvert installation.
  • 16th Street between Rev. Abraham Woods and 10th Avenue N will be closed Thursday, March 26th through Thursday, April 2nd from 12 a.m. […]
Weekly Update 03/26/202020-04-03T01:51:22+00:00
Thu 26/03/20

ALDOT Keeps Essential Services Going for Alabama

2020-03-26T23:05:41+00:00

I-59/20 Bridge Project Update

March 26, 2020

FOR IMMEDIATE RELEASE

NEWS RELEASE

MONTGOMERY, Ala. — The Alabama Department of Transportation (ALDOT) is maintaining essential services, such as road and bridge maintenance and construction, during the continuation of a national effort to prevent the spread of COVID-19. Work to repair slides and other roadway failures resulting from the recent record rainfall is also ongoing.

“ALDOT’s mission is to move people and goods, and that includes things such as products to keep stores stocked and supplies for healthcare providers and manufacturers of the equipment needed for community safety and sanitation,” said George Conner, […]

ALDOT Keeps Essential Services Going for Alabama2020-03-26T23:05:41+00:00
Tue 24/03/20

Weekly Update 03/24/20

2020-03-26T23:13:02+00:00

I-59/20 Bridge Project Update

March 24, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting:

  • The I-59 southbound off ramp to Carraway Blvd./ Red Mountain Expressway southbound ramp will be closed Tuesday, March 24th through Thursday, March 26th between 11 p.m. and 5 a.m. for painting operations.

Detour signs will be in place where necessary. Please keep in mind that all construction plans can change due to […]

Weekly Update 03/24/202020-03-26T23:13:02+00:00
Fri 20/03/20

Weekly Update 03/20/20

2020-03-24T21:23:17+00:00

I-59/20 Bridge Project Update

March 20, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting as follows:

  • The Red Mountain Expressway northbound ramp to I-59/20 North and I-20 East towards the Shuttlesworth International Airport will be closed Wednesday, March 25th at 9 p.m. thru 7 a.m., Monday, March 30th  to complete the construction of the bridge ramp.
  • The detour route will be 1st Avenue North and Caraway Blvd.

Detour […]

Weekly Update 03/20/202020-03-24T21:23:17+00:00
Thu 19/03/20

Weekly Update 03/19/20

2020-03-21T03:32:10+00:00

I-59/20 Bridge Project Update

March 19, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting:

  • 25th Street North between Rev. Abraham Woods Jr. Blvd. and Richard Arrington Jr. Blvd. will be closed, Tuesday, March 24th from 6 a.m. thru Friday, March 27th at 6 a.m. for Painting.
  • 19th Street North from Rev. Abraham Woods to 10th Street will be closed, Thursday, March 19th thru Thursday, March 26th from 12 a.m. until 11: 59 p.m. for Culvert Installation.
  • 16th Street between […]
Weekly Update 03/19/202020-03-21T03:32:10+00:00
Thu 12/03/20

Weekly Update 03/12/20

2020-03-19T15:29:56+00:00

I-59/20 Bridge Project Update

March 12, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting:

  • 23rd Street from Rev. Abraham Woods Jr. Blvd. to 9th Avenue N will be closed, Saturday, March 14th thru Monday, March 16th from 12 a.m. until 6 a.m. for Roadwork and Painting.
  • 22nd Street from Rev. Abraham Woods Jr. Blvd. to 9th Avenue N will be closed, Tuesday, March 17th thru Friday, March 20th from 12 a.m. until 11:59 p.m. for Roadwork and Painting.
  • 19th Street […]
Weekly Update 03/12/202020-03-19T15:29:56+00:00
Thu 05/03/20

Weekly Update 03/05/20

2020-03-12T16:34:58+00:00

I-59/20 Bridge Project Update

March 5, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting as follows:

  • 19th Street North from Rev. Abraham Woods to 10th Street will be closed, Thursday, March 5th for approximately one month for Culvert Installation.
  • 16th Street between Rev. Abraham Woods and 10th Avenue North will be closed Monday, March 5th thru Thursday, March 12th from 12 a.m. until 11:59 p.m. to install Drainage.
  • Richard Arrington Jr. Blvd. between Caraway and 28th Street will be […]
Weekly Update 03/05/202020-03-12T16:34:58+00:00
Fri 28/02/20

Weekly Update 02/27/20

2020-03-05T22:29:32+00:00

I-59/20 Bridge Project Update

February 27, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting as follows:

  • 19th Street North from Rev. Abraham Woods to 10th Street will be temporarily closed for Culvert Installation.
  • 16th Street between Rev. Abraham Woods and 10th   Avenue North will be closed Monday, February 27th thru Thursday, March 5th from 12 a.m. until 11:59 p.m. to install Drainage.
  • Richard Arrington Jr. Blvd. between Caraway and 28th Street will be closed Thursday, February 27th thru […]
Weekly Update 02/27/202020-03-05T22:29:32+00:00
Fri 21/02/20

Weekly Update 02/20/20

2020-02-28T16:40:48+00:00

I-59/20 Bridge Project Update

February 20, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting as follows:

  • 19th Street North from Rev. Abraham Woods to 10th Street will be temporarily closed for Culvert Installation.
  • 16th Street between Rev. Abraham Woods and 10th   Avenue North will be closed Monday, February 24th thru Thursday, February 27th from 12 a.m. until 11:59 p.m. to install Drainage.
  • Richard Arrington Jr. Blvd. between Caraway […]
Weekly Update 02/20/202020-02-28T16:40:48+00:00
Sat 15/02/20

Weekly Update 02/13/20

2020-02-21T03:21:46+00:00

I-59/20 Bridge Project Update

February 13, 2020

FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM– As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting as follows:

  • 19th Street North from Rev. Abraham Woods to 10th Street will be closed, Thursday, January 30th for approximately two months for Culvert Installation.
  • Richard Arrington Jr. Blvd. between Caraway and 28th Street will be closed Thursday, February 13th thru Thursday, February 20th from 12 a.m. until 11:59 p.m. for Roadway Work and Painting.
  • Richard Arrington Jr. Blvd. between 25th Street and Carraway […]