Weekly Update 03/29/19

2019-04-09T02:12:04+00:00

I-59/20 Bridge Project Update

March 29, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting, during the reconstruction of the new CBD Bridges:

  • Richard Arrington Jr. Blvd. between Carraway Blvd. and 25th Street N will close Saturday, March 30th from 7 a.m. until 10 a.m. to move a crane.
  • 16th Street N between 9th Avenue N and Rev. Abraham Woods will close Monday, April 1st from 8 p.m. until 11:59 p.m. to move […]
Weekly Update 03/29/192019-04-09T02:12:04+00:00
Thu 21/03/19

Carraway Blvd. Closures March 20th-23rd

2019-03-26T21:31:06+00:00

I-59/20 Bridge Project Update

March 20, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting, during the removal of the existing structures:

  • Single right lane closure at Carraway Blvd., southbound between 11th Avenue N and 26th Street N., Wednesday, March 20th from 9 p.m. until Thursday, March 21th at 5 a.m. to deliver girders.
  • Full closure of Carraway Blvd between 11th Avenue N and 26th Street N., Thursday, March 21st at 11 p.m. […]
Carraway Blvd. Closures March 20th-23rd2019-03-26T21:31:06+00:00
Sat 16/03/19

Closures on 23rd St N and 15th St N

2019-05-10T20:44:30+00:00

I-59/20 Bridge Project Update

April 29, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

Listed below are the current city streets that are open/closed beneath the CBD bridges during the reconstruction of the bridges:

Open

  • 16th Street N
  • 18th Street N
  • 19th Street N
  • Richard Arrington Jr. Blvd., between 9th Avenue & Rev. Abraham Woods Jr. Blvd.
  • 22nd Street N
  • 24th Street N
  • 25th Street N

Closed

  • 15th Street N
  • 23rd Street N

9th […]

Closures on 23rd St N and 15th St N2019-05-10T20:44:30+00:00
Wed 13/03/19

Project Update 03/13/19

2019-03-13T14:52:54+00:00

I-59/20 Bridge Project Update

March 13, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting, during the removal of the existing structures:

  • Carraway Blvd. between 11th Avenue and 26th Street North will be closed Wednesday, March 13th from 11 p.m. until 5 a.m. for crane mobilization.

Detour signs will be in place where necessary. Please keep in mind that all construction plans can change due to weather and other factors. As […]

Project Update 03/13/192019-03-13T14:52:54+00:00
Tue 12/03/19

Project Update 03/12/19

2019-03-13T14:45:04+00:00

I-59/20 Bridge Project Update

March 12, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

Listed below are current city streets beneath the CBD bridges that are open/closed during the demo and reconstruction of the bridges:

Open

  • 16th Street N
  • 18th Street N
  • 19th Street N
  • Richard Arrington Jr. Blvd., between 9th Avenue & Rev. Abraham Woods Jr. Blvd.
  • 22nd Street N
  • 23rd Street N
  • 25th Street N

Closed

  • 15th Street N
  • 24th […]
Project Update 03/12/192019-03-13T14:45:04+00:00
Mon 11/03/19

Project Update 03/11/19

2019-03-11T23:16:52+00:00

I-59/20 Bridge Project Update

March 11, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–The Alabama Department of Transportation is pleased to announce the installation of the first new bridge segment as part of the I-59/20 Central Business District (CBD) Interchange and Bridge Replacement Project. The segment was installed by contractors the morning of March 11th at the construction site on the corner of 19th Street North and 9th Avenue North. 

In an effort to expedite the construction process, most of the bridge’s 2316 segments have been […]

Project Update 03/11/192019-03-11T23:16:52+00:00
Tue 05/03/19

Project Update 03/05/19

2019-03-13T14:44:00+00:00

I-59/20 Bridge Project Update

March 5, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

Listed below are current city streets beneath the CBD bridges that are open/closed during the demo and reconstruction of the bridges:

Open

  • 16th Street N
  • 18th Street N
  • 19th Street N
  • Richard Arrington Jr. Blvd. – between 9th Avenue & Rev. Abraham Woods Jr Blvd.
  • 22nd Street N
  • 25th Street N

Closed

  • 15th Street N
  • 23rd Street N
  • […]

Project Update 03/05/192019-03-13T14:44:00+00:00
Sat 02/03/19

Project Update 03/01/19

2019-03-02T01:52:31+00:00

I-59/20 Bridge Project Update

March 1, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

Listed below are current city streets beneath the CBD bridges that are open/closed during the demo and reconstruction of the bridges:

Open

  • 16th Street N
  • 18th Street N
  • 19th Street N
  • Richard Arrington Jr. Blvd., between 9th Avenue & Rev. Abraham Woods Jr. Blvd.
  • 22nd Street N
  • 25th Street N

Closed

  • 15th Street N
  • 23rd Street N
  • 24th Street N

Motorists […]

Project Update 03/01/192019-03-02T01:52:31+00:00
Thu 28/02/19

Project Update 02/28/19

2019-03-01T00:23:30+00:00

I-59/20 Bridge Project Weekly Update

February 28, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting, during the removal of the existing structures:

  • Red Mountain Expressway to 59/20 NB will close, Thursday, February 28th from 11 p.m. until 5 a.m. for bridge girder erections.
  • Carraway NB closure will become a single left lane closure tonight, February 28th or Friday, March 1st from 11 p.m. until 5 a.m. to restripe the roadway […]
Project Update 02/28/192019-03-01T00:23:30+00:00
Wed 27/02/19

Project Update 02/27/19

2019-03-01T00:23:39+00:00

I-59/20 Bridge Project Weekly Update

February 27, 2019
FOR IMMEDIATE RELEASE

MEDIA ADVISORY
I-59/20 Bridge Project Update
(CBD) Central Business District Project

BIRMINGHAM–As construction continues in downtown Birmingham for Interstate Improvements, the Alabama Department of Transportation says drivers should expect delays.

The following closures will take place weather permitting, during the removal of the existing structures:

  • Carraway exit ramp from 59/20 SB will close Monday, February 25th and Thursday, February 28th from11 p.m. until 5 a.m. for bridge demo and girder erection.
  • Red Mountain Expressway NB to 59/20 NB ramp closure will take place each night, Monday, February 25th thru Thursday, February 28th from 11 p.m. […]
Project Update 02/27/192019-03-01T00:23:39+00:00
Load More Posts

59/20 Bridge Hotline

Phone: 205-346-5080

Media Contact: Linda Crockett

ALDOT East Central Region
100 Corporate Pkwy Ste 450
Hoover, AL 35242

Phone: 205-327-4973

GALLERY

RECENT POSTS